GB/Z 22135-2008 Milestones and activities during commissioning of electrical instrumentation and control systems in the process industry
GB/Z 22135-2008 Milestones and activities during commissioning of electrical instrumentation and control systems in the process industry
Basic Information
Standard Code:
GB/Z 22135-2008
Standard Type:
National standards
Standard Status:
Replaced
is_force_gb:
no
CCS Name:
Industrial automation instrumentation and control devices
ICS Name:
Integrated Industrial Automation System
Publish Date:
2008-06-18
Implement Date:
2009-01-01
Pages:
26 pages
Scope
This guidance technical document defines the stages and milestones in debugging (Figure 1), and describes, by way of example, the activities carried out by the owner after the "construction completion" milestone and before the factory acceptance. These activities will apply to various processes/factories.
Development Information
Superseded by the following standards
Adopt standards
IEC/PAS 62337:2002
Related Standards
GB 16655-1996
Replaced
GB 16655-1996 Industrial automation systems—Safety of integrated manufacturing systems—Basic requirements
GB/T 16720.1-1996
Replaced
GB/T 16720.1-1996 Industrial automation systems—Manufacturing message specification(MMS)—Part 1:Service definition
GB/T 16720.2-1996
Replaced
GB/T 16720.2-1996 Industrial automation systems—Manufacturing Message Specification(MMS)—Part 2:Protocol specification
GB/T 16721-1996
Replaced
GB/T 16721-1996 Industrial automation systems—Specification of subsets of the protocol for the manufacturing—Message specification
GB/T 16979.1-1997
Replaced