GB/T 31487.3-2025 Pending National standards

GB/T 31487.3-2025 Direct current deicers—Part 3:Tests

GB/T 31487.3-2025 Direct current deicers—Part 3:Tests

Publish Date: 2025-12-31 Implement Date: 2026-07-01 For services related to genuine standard inquiry, procurement, translation, and other related services in China, please Contact Us

Basic Information

Standard Code: GB/T 31487.3-2025
Standard Type: National standards
Standard Status: Pending
is_force_gb: no
CCS Name: Power semiconductor devices and components
ICS Name: Other equipment related to the transmission and distribution networks
Publish Date: 2025-12-31
Implement Date: 2026-07-01
Publisher: 国家市场监督管理总局、国家标准化管理委员会
Technical Committee: 全国电力电子系统和设备标准化技术委员会(SAC/TC 60)
Pages: 36 pages

Scope

本文件描述了直流融冰装置型式试验、例行试验、现场试验和维护试验的方法。
本文件适用于110 kV及以上交流输电线路导线和地线、直流输电线路地线融冰的电网换相直流融冰装置和模块化多电平直流融冰装置,其他类型直流融冰装置参照使用。

Development Information

Drafting Units:

南方电网科学研究院有限责任公司、西安高压电器研究院股份有限公司、电力规划总院有限公司、贵州电网有限责任公司电力科学研究院、西安电力电子技术研究所有限公司、中国南方电网有限责任公司、中国南方电网有限责任公司超高压输电公司、南京南瑞继保电气有限公司、北京四方继保自动化股份有限公司、中电普瑞科技有限公司、中国能源建设集团南京线路器材有限公司、中国电力工程顾问集团西南电力设计院有限公司、南方电网新型电力系统(北京)研究院有限公司、广州高澜节能技术股份有限公司、许继电气股份有限公司、河南晶锐冷却技术股份有限公司、西安西电电力系统有限公司、广东电网有限责任公司电力科学研究院、国网浙江省电力有限公司电力科学研究院、云南电网有限责任公司电力科学研究院、中国电力工程顾问集团西北电力设计院有限公司、中国电力工程顾问集团中南电力设计院有限公司、中国电力科学研究院有限公司、南方电网能源发展研究院有限责任公司、中国华能集团清洁能源技术研究院有限公司、福州大学、清华四川能源互联网研究院、国网四川省电力公司电力科学研究院、南方电网电力科技股份有限公司、广东福德电子有限公司、西南交通大学、国网福建省电力有限公司电力科学研究院、国网山西省电力公司电力科学研究院、广东电网有限责任公司、国网江西省电力有限公司电力科学研究院、天津大学、哈尔滨工业大学、华北电力大学、湖南长高高压开关有限公司、明珠电气有限公司、湖南福德电气有限公司、特变电工衡阳变压器有限公司

Drafting Persons:

魏伟、辛清明、许钒、傅闯、雷鸣、杨晓辉、李欢、周月宾、周会高、毛先胤、钟尧、王皆庆、任孟干、蔚红旗、冯俊杰、刘涛、李凌飞、侯婷、代书龙、黄超、董添华、邹常跃、赵晓斌、许树楷、王秀环、曾华荣、李婧靓、李英、秦康、李长伟、曹鹏、杨旗、唐金昆、徐望圣、奚鑫泽、洪权炜、田杰、张翔、许建中、雷鸣、刘伟、张雪垠、班国邦、廖名洋、吴越、杨柳、熊岩、万启发、谢惠藩、李应宏、张怿宁、方红伟、龚博、李昊、王泽昊、李斌、王立平、何佳伟、张露松、张建平、王琦、李彬彬、高勇、王强、陈锐、王小岭、梁宁、王成昊、王杰峰、马晓红、廖汉卿、刘湘、周陈韬、刘劲松、付峥争、吴冇、彭向阳、林旭涛、黄石华、任孝东、饶斌斌、卢仰泽、林才华、赵琳、黄桂灶、杨勇、李琦、何鑫、侯小平、王金柯、胡永雄、吴奇钢、熊水林、王立华、丘淼生

Word Count: 57 Thousand words Pages: 36 pages

Same series standard

Replace the following standards

Referenced Standards

GB/T 1094.1-2013 Power transformers—Part 1:General GB/T 1094.3-2017 Power transformers—Part 3:Insulation levels,dielectric tests and external clearances in air GB/T 1094.4-2005 Power transformers—Part 4:Guide to the lightning impulse and switching impulse testing—Power transformers and reactors GB/T 1094.11-2022 Power transformers—Part 11:Dry-type transformers GB/T 7354-2018 High-voltage test techniques—Partial discharge measurements GB/T 16927.1-1997 High-voltage test techniques Part 1:General test requirements GB/T 16927.1-2011 High-voltage test techniques—Part 1:General definitions and test requirements GB/T 20297-2006 Static var compensator field tests GB/T 20990.1-2020 Thyristor valves for high voltage direct current (HVDC) power transmission—Part 1:Electrical testing GB/T 25092-2010 Dry-type air-core smoothing reactors for HVDC applications GB/T 33348-2024 Voltage sourced converter valves for high-voltage direct current power transmission—Electrical testing GB/T 37008-2018 Technical specification of reactors for VSC-HVDC applications GB 50150-2016 Electric equipment installation engineering - standard for hand-over test of electric equipment GB 50171-2012 Code for construction and acceptance of switchboard outfit complete cubicle and secondary circuit electric equipment installation engineering DL/T 1215.4-2013 Chain-type Static Synchronous Compensator Part 4: Field Test GB/T 31487.2-2025 Direct current deicers—Part 2:Converters GB/T 31487.1-2025 Direct current deicers—Part 1:System design